Removing Steel Extension Platforms on MV AGIA EIRINI FORCE's weather-deck

Cập nhật: 02-02-2020 08:20:21 | Projects Update | Lượt xem: 1031

The first project after Lunar New year in Vietnam. We've been working so hard to remove steel extension platforms on the ship's weather-deck.

 

At 07:00 lt's 31/01/2020 our team arrived Vung Ang port with full equipments and started to prepare working.

MV AGIA EIRINI FORCE was on charter to us during 2019 performing (among others) a voyage with wind-energy cargo. For that voyage she was be installed 8 x steel extension platforms on several points on the ship’s weather-deck. Although the vessel has since been redelivered to head-owners, she still need to remove these steel extension platforms at a convenient port.

Image for Removing Steel Extension Platforms in Vung Ang Port.

After cutting, the cut-off extension platforms are considered scrap.

Moving scrap to shore.

We've done special job within 2 days.

Contact us:

Haiphong Marine Services Co. Ltd

Address: 27/633 Thien Loi street - Le Chan District - Hai Phong City

Email: info@haiphongmarine.com

Phone number: +84 947 739 556 - HOTLINE: +84 947 739 556

http://haiphongmarine.com